U-Match Series Service Manual
48
1.2.3 Installing the Main Body Unit
Figure 3-1-25
(1) Install the hoisting stand on the hoisting screw by using nuts and gaskets at both the upper and
lower sides of the hoisting stand. To prevent the gasket from breaking off, a gasket anchor
board can be helpful.
(2) Install the paper template on the unit, and fix the drain pipe at the outlet vent.
(3) Adjust the unit to the best position.
(4) Check if the unit is installed horizontally at four directions. If not, the water pump and the float
switch would function improperly and even lead to water leakage.
(5) Remove the gasket anchor board and tighten the nut remained.
(6). Remove the paper template.
1.2.4 Installing the Suspension Bolts
(1) Using the installation template, drill holes for bolts (four holes). (Figure 3-1-26)
(2) Install the bolts to the ceiling at a place strong enough to hang the unit. Mark the bolt positions
from the installation template. With a concrete drill, drill for 12.7 mm (1/2”) diameter holes.
(Figure 3-1-27)
(3) Insert the anchor bolts into the drilled holes, and drive the pins completely into the anchor bolts
with a hammer. (Figure 3-1-28)
Figure 3-1-26 Figure 3-1-27 Figure 3-1-28