Photovoltaic Multi VRF
24
Description of each stage of debugging progress
Code meaning and operation
method
System finishes confirmation.
2s later, next step starts.
04_ Confirm
the quantity of
IDU
LED3 displays the quantity of
indoor unit. Confirm the
number manually. If the
number is not consistent the
display one, cut off power of
IDU and ODU and check
whether communication wire
of IDU is correctly
connected. After the check,
connect power and start
debugging from progress 01. If
the number is then correct,
press main board’s SW7
button to confirm. Then the
display is as below:
System has confirmed the
quantity. 2s later, next step
starts.
05_ Detect
ODU’s internal
communication
and capacity
ratio
Communication between
master ODU and driver has
error. Check the
communication connection
of ODU’s main board and
drive board. When the error is
eliminated, start next step. If
power is off during
troubleshooting, then restart
debugging from progress 01
after power is on.
Communication of master
ODU and driver is normal. Unit
will display as in the left for 2s
and detect the capacity ratio of
IDU and ODU. If the ratio is
within range, than next step will
start 2s later. If the ratio is out
of range, unit will display as
below: