GREE         U-Match 5 SERIES UNIT SERVICE MANUAL 
92 
(6)   Wait for 10min to see if the system pressure can remain unchanged. If the pressure increase, there may be 
leakage. 
(7)   Slightly open the liquid valve and let some refrigerant go to the connection pipe to balance the pressure 
inside and outside of the connection pipe, so that air will not come into the connection pipe when removing 
the hose. Notice that the gas and liquid valve can be opened fully only after the manifold valve assembly is 
removed. 
(8)   Place back the caps of the liquid valve, gas valve and also the service port. 
 
 
NOTICE:
 
For large-size units, there are maintenance ports for liquid valve and gas valve. During evacuation, you may 
connect the two hoses of the branch valve assembly to the maintenance ports to speed up the evacuation.   
Refrigerant should be reclaimed into the appropriate storage tank. System should use oxygen-free nitrogen 
purging to ensure safety. This process may need to repeat several times. Do not use compressed air or oxygen in 
this process.   
4.3 Refrigerant Charging 
Pre-charging 
Step 1: Connect the high pressure gauge line to the valve of liquid pipe and connect the low pressure gauge 
line to the valve of gas pipe. Connect the middle gauge line to the vacuum pump. Power on the vacuum pump 
and perform vacuum drying. 
Step 2: After vacuum drying, close the high and low pressure gauge valves. Then remove the middle gauge 
line from the connector of vacuum pump. Then connect to the refrigerant tank. 
Step 3: Loosen the middle gauge line from the connector of pressure gauge to a proper extent and slightly