5.4 Installation Foundation and Service Space
(1)Installation foundation shall be designed by the qualified designer in accordance with
the actual condition.
(2)A rubber pad shall be placed under the base of each single unit and then secured on
the ground or the roof. Alternatively, each single unit can be placed side by side on the
parallel channel steel with enough strength which then shall be secured with anchor
bolts. Distance between each single unit shall be keep 0.5m as a minimal.
(3)Enough space shall be left for service and ventilation. Be sure there is at least 2m
between the equipment and any barrier and it is better to set up a sun cover 3m ahead
of the equipment.
(4)The unit shall be installed where it will not be affected by fire, corrosive, inflammable or
waste gas, and proper measures shall be taken to minimize the vibration and noise.
(5)The unit shall be installed where the defrosting water can be drained out favorably
(6)Do not install the unit where there is heavy snow. If inevitable, build a foundation at
least 300mm higher than the ground.
Installation Space for the Single Unit
(Unitmm)
Installation Space for Modularized Units
(Unitmm)
A Series Inverter Modular Air-cooled Chiller (Heat Pump)

Other manuals for Gree LSQWRF65VM/NaA-M

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Gree LSQWRF65VM/NaA-M and is the answer not in the manual?

Gree LSQWRF65VM/NaA-M Specifications

General IconGeneral
BrandGree
ModelLSQWRF65VM/NaA-M
CategoryChiller
LanguageEnglish

Related product manuals