EasyManua.ls Logo

Gulf+Western ACWC-SC - Location & Mounting; Wiring; Chiller Piping; Start-Up

Default Icon
19 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
INSPECTION
&
HANDLING
When
unit
is received,
it
should
be
checked
for
visible
or
concealed
damage
. If
damage
has
occurred
it
should
be reported
to
the carrier
imm
e
diately
.
o.nd
clo.im
filed
.
Models
ACWC
160SC
thru
215SC are
factory
mounted
on
two
(2)
permanent
angle beam,
carbon
steel skids. Ei
ght
(8) 2W'
lifting
eyes
are
provided
in the
skids
to
allow
rigging.
Spreader bars
must
be
used between
rigging
lines
to
prevent
damage
to
the
unit. Rollers
may be used
under
the
skids
to
facilitate
moving
the
unit
a
short
distance
. Physical damage to the unit, after acceptance,
Is
not the
responsibility of the factory.
LOCATION
&
MOUNTING
Model
ACWC
Air
Cooled
Packaged Water
Chillers
are
designed
for
outdoor
application
and
may
be
mounted
on
roof
or
at
ground
level.
Air
flow
through
the
condenser
is vertical and the
unit
may be
located
adjacent
to
outside
of
building
or
on
roof
without
regard
for
prevailing
wind
direction.
Since
these
units
are
air
cooled,
the
flow
of
air
to
and
from
the
condenser
coil
must
not
be impeded.
There
must
be
no
obstruction
above the
unit
that
would
tend
to
deflect
discharge
air
downward
where
it
could
be
recirculated
back
to the
inlet
of
the unit. The
required
overhead
air
space
should
be a
minimum
of
eight
(8) feet.
Ductwork
must
not
be applied
to
the fan
outlets
.
The
unit
must
be
installed
with
sufficient
clearance
for
air
entrance
to
the
condenser
coil
and
for
servicing
access. The
unit
should
be
located
no
closer than
four
(4) feet
from
any wall
or
other
obstruction
.
Clearance
must
be
provided
at
either
end
of
the
unit
to
permit
removal
of
tubes
from
the
chiller
.
Unit
must be set on a
solid
and level
foundation
.
On
roof
installations
the
unit
should
be
mounted
on
support
beams
which
span
load-bearing
walls
to
prevent excessive
vibration
.
On
ground
level
installations,
the
unit
should
be
mounted
on a
substantial
base
that
will
not
settle. A
one-piece
concrete
slab
with
footings
extended
below
the
frost
line is recommended. A space
should
be left between the
slab
and
the
building
to
prevent
the
transmission
of
sound
and
vibration
.
Vibration
mounts
may
be used
for
roof
mounted
units
or
other
locations
where noise
might
be
objectionable.
WIRING
A
unit
wiring
diagram
showing
the required
power
supply
character-
istics
and all
factory
supplied
wiring
details is
provided
with
unit.
Separate, field
supplied,
disconnects
must be installed in the
power
supply
and
should
be
within
the
sight
of
the unit.
Separate 115
volt
power
source
must be field
supplied
to
provide
power
for
control
and heater
circuits
.
2
CHILLER
PIPING
The
chiller
inlet
(return)
water
pipe
should
be
connected
to the water
connection
closest
to
the
control
panel end
of
the
unit
and the
outlet
(:.upply)
vvdte• 1-'ifJt::
<..v""""'t"'u
tv
u,.,
wat.,r
<,;urrrr.,<,;llun
on
the
opposite
end
of
the cooler(s).
A
flow
switch
must
be installed in a
straight
horizontal
section
of
the
chilled
water
piping
.
Gauges
should
be installed in
the
piping
to
and
from
the
chiller
to
measure
the
pressure
drop
and to
insure
the
proper
(GPM)
flow
rate
in
accordance
with
submittal
data. A
strainer
should
be
installed
in
the
piping
on the
inlet
side
of
the
chiller
and
vibration
eliminators
should
be
employed
on both the inlet and
outlet
pipes.
Air
vents
should
be located at all high
points
in the
piping
system. Vents
should
be located
to
be accessible
to
servicing
. Drain
connections
should
be
provided
at all
low
points
to
permit
complete
drainage
of
chiller
and
piping
system.
The
chilled
water
piping
should
be
insulated
to
reduce heat
pickup
and
to
prevent
condensation
.
If
the system is
for
year-round
operation
or
if
it
will
not
be
drained
in the winter,
the
chilled
water
piping
should
be protected against freezing by
electric
heating cable
or
other
suitable means.
Upon
completion
of
chiller
piping,
start
the
system water
pump
and
purge
air
from
the
system.
Air
purging
should
be
done
from
the
high
points
in
the
water
circuit.
Purging
of
the
chiller
barrel may be
accomplished
through
the
vent
pipe
located
on
the
top
of
the
chiller
compartment.
Failure
to
purge
air
from
the
water
circuit
will
result in
inadequate
waterflow
and may cause the
unit
to
cutout
on
low
water
flow
freeze
protection.
START-UP
Refer
to
start, test, and
check
list
included
with
this
manual.
Check
all
electrical
and
mechanical
connections
for
shipping
looseness and
tighten
all screws on electrical
terminals
.
Activate the 115
volt
chiller
and crankcase heater
circuit
24
hours
prior
to
unit
start-up
.
Rotate each fan
prior
to
start-up
. Fans
should
turn
freely.
Check
belt
tension
and
pulley
alignment.
After
two
(2) weeks
of
operation,
readjust
belt
tension
to
accommodate
for
belt stretching.
Check
all
control
settings
as
specified in Table
1.
Check
the
compressor
oil level
through
the
crankcase
sight
glass.
The
oil
level
should
be
to
the
top
of
the glass. If
the
level is low, add
oil in
accordance
with
the
directions
in the
maintenance
instruction
(page 3).
..
.
--..,_