2
CAUTION
Pre-Installation Check
Ensure that the equipment room, cabinets, power supplies, ground cables, optical cables, and associated devices are ready for
installation. Start the installation according to the engineering design documents after confirming that all conditions are met.
Bundling Cables
Binding intervals between cable ties or optical fiber binding straps inside the cabinet cannot exceed 250 mm. (Binding intervals
cannot exceed 200 mm for user cables.)
Binding intervals between cable ties for all cables and corrugated pipes outside the cabinet are determined based on the distance
between the two horizontal beams. If the cable trough does not contain any beams, the binding intervals between cable ties cannot
exceed 250 mm.
CAUTION
Installation Precautions
ESD jacks on the universal platform subrack
ESD jacks on the T16 subrack