87
T16
T16
9 Installing and Routing Subrack Power Cables
T16 Subrack
c
When power cables are preinstalled on the right side of a cabinet
When a T16 subrack needs to be installed on site, power cables are preinstalled on the right
side of the cabinet if the subrack is co-resident with T64/T32 subracks.
NOTE
Route the preinstalled power cables to the left and right sides of the T16 subracks.
Main power cables: Route the cables from the right side to the left side of the subrack along the empty
space above the subrack.
Backup power cables: Directly route the cables to the right side of the subrack.
Main
Backup
Main
Backup