Page #74 background image
8.27
Section 8
Electrical System and Components
8
Test 4 Solenoid Hold-In Coil/Contact Continuity Test
Use an ohmmeter set to the audible or Rx2K scale, and
connect the two ohmmeter leads to the two large post
terminals. Perform the preceding test (3) and check for
continuity. See Figure 8-61. The meter should indicate
continuity, if no continuity is indicated the solenoid
should be replaced. Repeat test several times to
confirm condition.
Figure 8-61. Testing Hold-In Coil/Solenoid Contact
Continuity.
Plunger
Pushed In
VOM Meter
Leads
12 volt Test Leads

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Kohler Command CH13 and is the answer not in the manual?

Kohler Command CH13 Specifications

General IconGeneral
BrandKohler
ModelCommand CH13
CategoryEngine
LanguageEnglish

Related product manuals