Drain pipe insulation
- Drain pipe should be insulated all connected joints and ends.
- Do not use the loose fitting insulation.
Drain water leakage test
- Water leakage test should be performed 24 hours later after drain work finishing.
- In the test, only water should be used. Other liquids are unacceptable.
Insulation
required
Insulation
not required
Loose fitting
wrong insulation
Fitting insulation
2. Guideline for each installation process
18 _ Heat pump 60Hz/R410A
Installation of
Outdoor Units
SINGLE ZONE