7. Reseat AYK1 circuit pack. Verify AYK1 and AYK2 circuit packs are fully
seated. On AYK1 and AYK2, verify all circuit breakers are set (pins pushed
in).
8. On right-hand side of shelf [Figure 3], verify alarm cable is connected with
J4
connector firmly seated in
P4
socket [Figure 3].
9.
NOTE:
The
FBAT
and
FRB
fuses are factory installed and should not be
removed.
On control & distribution panel, verify
FBAT
and
FRB
fuse holders are
installed. On inside of panel cover, verify spare fuses are present and properly
installed in fuse holders.
10. Replace cover on control & distribution panel.
STOP. YOU HAVE COMPLETED THIS PROCEDURE.