RT Turn Up: NTP-004 363-205-401
Page 4 of 4 Issue 7, March 1997
DO ITEMS BELOW IN ORDER LISTED FOR DETAILS, GO TO
10.
NOTE:
All
LIU
s in the same system should have identical option
switch settings.
NOTE:
FPB Mode 2 does not require an LIU in LIU-D slot. FPD
requires a TCU in LIU-D slot.
DLP-512Install DS1
LIU
in
LIU-D
slot in facility shelf after making option,
equalizer, and transmit pad settings for FPA, FPB Mode 1, FPC,
FPC-AutoCut, or FPF.
DLP-51511. If protection switching is being added, install associated
LSU
(line
switch unit) in facility shelf. Otherwise, proceed to Step
13
.
12.
NOTE:
All
LIU
s in the same system should have identical option
switch settings.
DLP-512Install associated DS1 protection
LIU
(if required) in
LIU-P
slot in
facility shelf after making option, equalizer, and transmit pad set-
tings.
DLP-51813. Perform RT indicator test.
14. Update office records.
15. Perform End-to-End tests in 363-205-406 TOP when required.