Conversions: NTP-010 363-205-401
Page 6 of 6 Issue 7, March 1997
DO ITEMS BELOW IN ORDER LISTED FOR DETAILS, GO TO
DLP-51515. Perform RT LED test.
16. Remove the ADU and set switches S1-3 and S1-4 to ABI and
CDI. Reinstall the ADU.
The
MJ
and
FE
LEDs on the
ADU
and
DIGROUP
LEDs on the
BCU
light.
17. Wait for the switch personnel to restore to service the IFACs
associated with the RT.
As each IFAC is restored to service, the
DIGROUP
LED on the
BCU
associated with the IFAC goes off. After all the
DIGROUP
LEDs go off, a
MN
and
FE
remains lighted until the protection
IFAC is restored.
18. Wait for the switch personnel at the MCC to provision the RT.
Response: Wait for the MCC to display
EXC RT PROV
TYPE=ALL SID=g LRT= d e f COMPLETED - NO
TASKS PENDING
(where g=Site ID number, d=SM
number, e=IDCU number, and f=FP303 RT number)
before continuing. Provisioning can take up to 15
minutes depending on the switch activity level.
19.
NOTE:
The next three steps verify correct end-to-end operation.
DLP-517Test alarm system for power minor and fan alarms.
DLP-51820. Test alarm system for miscellaneous alarms.
DLP-51921. Perform channel tests.
22. Update office records.