363-205-401 Power Up:
Issue 7, March 1997 Page 1 of 6
DLP-504
Perform Test of RT Batteries Using 197A Battery
Load Test Set
1.
!
CAUTION:
Service interruption will occur if batteries are disconnected and AC power
is not available.
Obtain
197A BATTERY LOAD TEST SET (197A)
and place near batteries to
be tested (Figure 1).
2.
NOTE:
The 197A test set is intended to test batteries that are fully charged. A
minimum of two days must be allowed between the time the batteries
(new or replacement) are put on high rate charge and this test is made.
After testing is completed, the batteries must be put on high rate charge
using the
337A BATTERY CHARGER
.
Remove cover from
197A
test set.
3. Check
197A
test set for proper operation (if not already performed).
Reference:
DLP-533
4. Ensure that system(s) associated with batteries to be tested has AC power
available (
PMN
or
P/M
indicator on
BCU
circuit pack not lighted).