11. Maintenance of MQM Quantometers
1. Quantometers without oil pump do not require special services.
They are maintenance-free.
2. Quantometerswithanoilpumprequireperiodicallymaintenance:
2.1. Lubricationevery2to3monthsifthegasiscleanandltered
upstreamthemeter:
DN50:2strokes,DN80:4strokes,DN100:4strokes,DN150:7strokes
2.2. If the gas is carrying dust and/or moisture then the lubrication has to be
done at least every month.
3. ArepairoftheQuantometerhasonlytobedonebycompetentandauthorized
personnelliketheServiceEngineersfromMetregTechnologies.
12. Commissioning of the MQM Quantometer
The start-up procedure of the MQM Quantometer follows the installation
and leakage test of the connections:
1. Openslowlytheupstreamvalve(g.2andg.3)
topressurizethepipeuntiloperationpressureisachieved.
2. The rate of pressure increase shall not exceed 350 mbar/s.
3. At operation pressure level open the upstream valve completely.
4. Slightlyopenthedownstreamvalve(g.2andg.3).
5. At operation pressure level the downstream valve
can be opened completely.
6. Performaleakagetestonthemeteratoperationpressure.
7. Removethestartupsieveafter4to6weeks(ifinstalled).
13. Decommissioning procedure of the MQM Quantometer
1. Takecareofappropriateventilationoftheinstallationroom.
2. Depressurizetoatmosphereonlytoareas
with no active ignition sources.
3. Reducetheoperatingpressureslowly(e.g.<350mbar/s).
4. Opentheboltsandnutsoftheangesonly
ifthepipeiscompletelydepressurized.
5. Carefullytakeoutthemeterfromthepipeconnection.