During vacuum drying, a vacuum pump is used to lower the pressure in the piping to the extent that any moisture 
present evaporates. At 5mmHg  (755mmHg  below typical atmospheric pressure)  the boiling  point of  water is  0°C. 
Therefore a vacuum pump capable of maintaining a pressure of -756mmHg or lower should be used. Using a vacuum 
pump with a discharge in excess of 4L/s and a precision level of 0.02mmHg is recommended. 
 
Caution 
  Before performing vacuum drying, make sure that all the outdoor unit stop valves are firmly closed. 
  Once the vacuum drying is complete and the vacuum pump is stopped, the low pressure in the piping could suck 
vacuum pump lubricant into the air conditioning system. The  same could happen if the vacuum pump stops 
unexpectedly during the vacuum drying procedure. Mixing of pump lubricant with compressor oil could cause 
compressor  malfunction  and  a  one-way  valve  should  therefore  be  used  to  prevent  vacuum  pump  lubricant 
seeping into the piping system. 
 
Procedure 
The vacuum drying procedure is as follows: 
Step 1 
  Connect the blue (low pressure side) hose of a pressure gauge to the master unit gas pipe stop valve, the red (high 
pressure side) hose to the master unit liquid pipe stop valve and the yellow hose to the vacuum pump. 
Step 2 
  Start the vacuum pump and then open the pressure gauge valves to start vacuum the system. 
  After 30 minutes, close the pressure gauge valves.   
  After a further 5 to 10 minutes check the pressure gauge. If the gauge has returned to zero, check for leakages in 
the refrigerant piping. 
Step 3 
  Re-open the pressure gauge valves and continue vacuum drying for at least 2 hours and until a pressure difference 
of 756mmHg or more has been achieved. Once the pressure difference of at least 756mmHg has been achieved, 
continue vacuum drying for 2 hours. 
Step 4 
  Close the pressure gauge valves and then stop the vacuum pump. 
  After 1 hour, check the pressure gauge. If the pressure in the piping has not increased, the procedure is finished. 
If the pressure has increased, check for leakages. 
  After vacuum drying, keep the blue and red hoses connected to the pressure gauge and to the master unit stop 
valves, in preparation for refrigerant charging (see Part 3, 8 “Charging Refrigerant”).