of 05 Page 04
Ø8
Studs Noggins
12V Wiring
Fixed
Wiring
Transformer
Wall Preparation
Installation - 1
Installation - 2
Ÿ Use the rail to mark centre fixing points.
Note: Ensure fixing point are level.
Ÿ
wall. Ensure Electrical Mounting Bracket is positioned at the wiring
connection leg.
Use supplied Wall Screws and Anchors to fix Mounting Brackets to
Ÿ
with supplied Allen key.
Ÿ Use Flat Grub Screw and supplied Allen key to attach Electrical Leg
to rail.
Attach Non-Electrical Legs using supplied Fasteners and tightening
Ÿ
Ÿ
Ÿ Stud walls (timber or steel) require timber noggins at the correct
position for the wiring connection leg.
Ÿ If the precise position can't be determined early in the job, consider
noggins with 18mm construction ply, covering a larger area.
Note: Fixing into plasterboard or cement sheeting alone is NOT
recommended.
Note:
timber stud, steel stud or masonry (solid or cavity).
Heated towel rails may be fixed to ANY type of wall,