Application
Use this procedure to check the capacity of Eagle Picher batteries in an
outside plant access cabinet (OPAC). The OPAC has a multiline test unit
(MTU).
Interval
Perform this procedure at intervals of six months when MTU measurements
comply to specifications. Perform this procedure at intervals of three
months if the MTU measurements do not comply to specifications.
Do not perform this procedure at the same time as the automatic battery test
procedure.
Common procedures
There are no common procedures.
Action
This procedure contains a summary flowchart and a step action procedure.
The summary flowchart provides an overview of the procedure. Use the list
of steps following the flowchart to perform this procedure.
Battery capacity test
OPAC
13-2 Routine maintenance procedures 13-213-2

Table of Contents

Other manuals for Nortel DMS-100 Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Nortel DMS-100 Series and is the answer not in the manual?

Nortel DMS-100 Series Specifications

General IconGeneral
CapacityUp to 100, 000 lines
FeaturesISDN support
RedundancyYes
SignalingSS7, ISDN
Power-48V DC

Related product manuals