EasyManua.ls Logo

Philips SCF870/22 - Page 7

Philips SCF870/22
9 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
SCF870/20 /21 /22 /23
7-9
2nd operation Assembly of the switch holder to the body
- Put the switch holder in position and screw 2 pcs of 2,9 x 16 screws with a torque between 0.50 - 0.60 Nm.
- Tidy up the cables as shown in the photos to prevent the cables from damages during boiler body assembly.
3rd operation Boiler body assembly
- Align the boiler body water inlet with the main body water inlet (shown with arrow in the photo below) and position the boiler
body.
- Screw 3 pcs of 3,5 x 13 screws with a torque between 0.72 - 0.84 Nm.
ATTENTION: Sealing tests that are completed on the production line are not meaningful (should be repeated) after boiler body
is reattached.
DISASSEMBLY- AND RE-ASSEMBLY ADVISE

Related product manuals