Be careful to assemble all components in the
sequence they are presented.
S T E P
6
Inch
MM
A. Slide Long Foam Roller Bar (86) into the opening in Lower Main Frame (A) as shown.
Slide two Plastic Washer (25) and two Foam Rollers (22) onto Long Foam Roller Bar (86) as shown.
Hold Foam Rollers (22) in place with two Plastic Roller End Cap (24) as shown.
B. Slide Foam Roller Bar (39) into the Seat Pad Frame (L) as shown.
Slide two Plastic Washer (25) and two Foam Rollers (22) onto Foam Roller Bar (39) as shown.
Hold Foam Rollers (22) in place with two Plastic Roller End Cap (24) as shown.
C. Slide Foam Roller Bar (86) into the Leg Extension Arm (K) as shown.
Slide two Plastic Washer (25) and two Foam Rollers (22) onto Foam Roller Bar (39) as shown.
Hold Foam Rollers (22) in place with two Plastic Roller End Cap (24) as shown.
D. You can now go through the main frame unit and double check all bolts and nuts are wrench tight.
Do NOT re-tighten any of the pad bolts.
Leave all pulley bolts hand tight until cable installation in step 10 is completed.