EasyManua.ls Logo

Rapido F 310 - Installation; Setting Up; Minimum Clearances; Water Supply-Side Connections

Rapido F 310
52 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
9
6 Installation
Installation must be carried out by a qualified technician,
who takes responsibility both for installation and for put-
ting the unit into operation, as laid down in regulations.
6.1 Setting up
When setting up, follow the Technical ground-rules for
planning and operation of heating systems  VDI
Guideline 2050. The height they specify for the base 
60 to 70 mm  should be observed, taking into account
that burners with downward-facing air intake manifold
require adequate clearance between air inlet and floor. It
may be necessary to use a higher base or a correspond-
ing recess in the floor. When installing several boilers
next to each other, there must be a minimum clearance
of 500 mm between boilers.
Noise insulation
To reduce the transmission of structure-born noise, spe-
cially made, tensioned, longitudinal insulation fasteners
are available for installation at the foot of the boiler.
We have measured the noise level  without exhaust
gas noise insulation  and this varies from 70  80 dBA,
according to make of burner, flue design, and load. This
value refers to a measuring point 1 m away from the roof
flue outlet.
If building conditions demand it, we recommend the in-
stallation of exhaust gas noise insulators.
A base for the boiler makes installing easier. Two sup-
port brackets are supplied for mounting under the foot of
the boiler.
If structure-noise absorbing elements (longitudinal insu-
lation fasteners) are used, special attention should be
paid to providing the boiler with an even surface to stand
on.
Longitudinal insulation fastener F 310
Stainless steel longitudinal insulation fastener as insulation element for
absorption of structure-born noise, consisting of damper in form of U-
bracket and RHS bracket for weight distribution (supplied as optional
extra).
6.2 Minimum clearances
To make installation and maintenance easier, the follow-
ing minimum clearances should be observed:
a) in front of boiler 1.500 mm
b) behind boiler 1.000 mm
c) on either side, at least 500 mm
6.3 Water supply-side connections
The heating advance and back-flow connections are in
the end section in the upper and lower boiler hub axis
extension (see Fig. 36, page 30). An opening is allowed
for in the back-flow connection elbow to permit boiler
filling and draining. Connect only those expansion tanks
that are permitted in the type of construction in question,
or which have been individually expert-tested. The safety
valve should be installed in the heating advance, in the
immediate vicinity of the boiler (valid for enclosed units).
Note on back-flow elevation
When installing in enclosed units, ensure that air is prop-
erly bled from the boiler and system. Sufficient circula-
tion must be maintained in the boiler under all operating
conditions.
A sufficient level is 1/3 of the water quantity correspond-
ing to the nominal boiler flow capacity.
To this end, the boiler must be pre-equipped with a cir-
culation pump of adequate capacity, installed between
the advance and back-flow (back-flow elevation).
Pump control is carried out via the rapidomatic
®
(acces-
sory).
No. of
sections
Weight Boiler length L Number and length of
longitudinal insulation
fasteners
kg mm A mm B mm C mm
9 1450 1350 2 x 250 2 x 375 2 x 250
10 1550 1500 2 x 375 2 x 375 2 x 250
11 1700 1650 2 x 375 2 x 375 2 x 375
12 1800 1800 2 x 375 2 x 375 2 x 375
13 1950 1950 2 x 375 2 x 500 2 x 375
14 2100 2100 2 x 500 2 x 500 2 x 375
15 2200 2250 2 x 500 2 x 500 2 x 375
16 2300 2400 2 x 500 2 x 500 2 x 375
boiler block
Detail A
Detail A
1 RHS profile tube 40 x 20 x 3
2 Type 3/1000 longitudinal
insulation fastener
3 U-rail 50 x 50 x 3
Dimensions of longitudinal insulation
fastener
For number and length of
longitudinal insulation
fasteners, see table

Related product manuals