Operator Manual
The AURA™ system is designed for installation in an oce or a clinic and requires minimal site
preparation. When the AURA™ system is purchased, complete on-site installation, including initial
system testing and calibration, is included.
System transportation and installation is carried out by authorized technical personnel, who will
do the following:
1.
Unpack the system and position it in its pre-selected location.
2.
Verify the integrity of the system and its components.
3.
Connect system components (module).
4.
Plug the system into a designated electrical outlet.
5.
Test the system for proper calibration and functional operation of all components and
software.
6.
Coordinate the performance of an on-site safety inspection, if required.
Note: Any damage to the packaging or to the system found prior to opening the package should be
reported to your REVEAL™ representative and to the insurance carrier.
3.1 Introduction
SECTION 3
System Installation
The System can automatically accommodate the most of the local mains voltage. Specically, the
System can be energized of the mains voltage as follow: (100V AC; 10A) or (115V AC; 10A) or (230V
AC; 10A) or (240V AC; 10A) 50-60Hz.
3.2 Electrical Requirements
8