8 VC Series Manual
24"
V
Check on whether local codes supersede these clearances.
Avoid terminaon locaons near a dryer vent.
Avoid terminaon locaons near commercial
cooking exhaust.
You must install a vent terminaon at least 12
inches from the ground.
60"
V
V
(1.52 m)
between
terminals at
dierent levels
(0.61 m) to wall or parapet
(0.30 m) between
terminals at same
level
12"
V V
(1.52 m) vercally
between terminals
V
60"
V
Addional clearances - RL75i, RL94i
12"
12"
36"
INSIDE
CORNER
V V
(0.30 m ) to
an inside
corner
(0.30 m) between
terminals at same
level
Important consideraons for locang vent
terminaon under a sot (venlated or unvenlated
or eave vent; or to a deck or porch)
Do not install vent terminaon under a sot vent
such that exhaust can enter the sot vent
Install vent terminaon such that exhaust and
rising moisture will not collect under
eaves. Discoloraon to the exterior of the
building could occur if installed too close.
Do not install the vent terminaon too close
under the sot where it could present
recirculaon of exhaust gases back into the
combuson air intake part of the terminaon.

Table of Contents

Other manuals for Rinnai RL75I

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Rinnai RL75I and is the answer not in the manual?

Rinnai RL75I Specifications

General IconGeneral
TypeTankless
Fuel TypeNatural Gas or Propane
Flow Rate7.5 GPM
Energy Factor0.82
Installation TypeIndoor
Max BTU180, 000 BTU
GPM @ 35° Rise7.5
Minimum BTU Input15, 000 BTU
VentingDirect Vent