Beacon 110 Operator’s Manual 11
NOTE: See “Chapter 3: Installation & Startup” on page 12 for complete Beacon 110
installation instructions.
CAUTION: Do not adjust the strobe brightness or the horn volume at the strobe/horn, as this
may overload the Beacon 110 strobe control circuit.
The optional horn/strobe is generally not factory installed and needs to be installed by the
user. The following instructions describe the installation of the horn/strobe. If the horn/
strobe is factory installed, the following instructions do not apply.
1. Mount the horn/strobe in the desired location.
2. Install an appropriately rated cable bushing or conduit to the left conduit hub on the
bottom of the Beacon 110 housing.
3. Install an appropriately rated cable bushing or conduit at the horn/strobe.
4. Run a cable or wires in conduit from the horn/strobe to the Beacon 110 through the left
conduit hub.
5. Connect the wires to the strobe terminal strip as shown in the figure below.
Figure 5: Horn/Strobe Wiring/Outline and Mounting Dimensions
+
Dimensions Shown in Inches
-
5.97
6.81
4.83
6.17
Strobe Terminal Strip