Installing a Universal Comm. Kit
Installing EEV Assembly (Not provided)
1. Check that EEV Assembly is installed inside the indoor unit.
where condensate water can be drained.
2. Check whether IN and OUT pipe connection is correct.
3. Essential to check the EEV Assembly main body is installed vertically.
4. Fix the EEV to indoor unit xing groove rmly as shown in the image A below.
A
B
Standard for vertical
installation
Standard for vertical
installation
Insulator
Clamp
A
5. For checking EEV service, please attach a label sticker.
sticker to valve wire housing.
6. Connect the EEV termial block to exact places on PCB according to set capacity.