22. COMMISSIONING REPORT
INSTALLING CONTRACTOR: …………………………………………………………….
COMMISSIONING TECHNICIAN: ………………………………………………………..
ADDRESS: …………………………………………………………….
CITY: …………………………………………………………….
STATE/PROV: …………………………………………………………….
PHONE: …………………………………………………………….
CELL: …………………………………………………………….
DATE INSTALLED: ……………………………
PROJECT NAME: …………………………………………………………….
PROJECT CITY: …………………………………………………………….
HEATER MODEL #: …………………………………………………………….
HEATER SERIAL #: …………………………………………………………….
THIS APPLIANCE HAS BEEN FACTORY TESTED PRIOR TO SHIPMENT.
HOWEVER, IT IS NOT A “PLUG-IN” APPLIANCE AND REQUIRES FIELD ADJUSTMENT
AND COMMISSIONING TO ENSURE SAFE AND EFFICIENT OPERATION.
A QUALIFIED GAS SERVICE TECHNICIAN MUST COMMISSION THE APPLIANCE AND
COMPLETE THE COMMISSIONING REPORT.
CONFIRM THAT THE APPLIANCE IS INSTALLED ACCORDING TO ALL LOCAL AND NA-
TIONAL CODES AND THE INSTRUCTIONS IN THIS MANUAL.
ENSURE THAT SITE CONDITIONS MEET THE SPECIFICATIONS IN THIS MANUAL RE-
GARDING:
 SUSPENSION
 CLEARANCES TO COMBUSTIBLE MATERIAL
 VENTING AND AIR SUPPLY
 ELECTRICAL SUPPLY, WIRING, AND CONNECTION
 GAS CONNECTION, SUPPLY AND MANIFOLD PRESSURE
THIS COMMISSIONING REPORT MUST BE SUBMITTED TO OUR TECHNICAL SER-
VICES DEPARTMENT PRIOR TO ANY CALL FOR TECHNICAL ASSISTANCE
.
FAX THE COMPLETED REPORT TO 1-866-361-0523
Call Technical Services: 1-877-446-3727