SCHWING GMBH – Separate Placing Booms SPB 02/2014
8
1x Working platform (386 Kg)
to facilitate the assembly and operation
of the equipment. The platform
can be reached via ladders.
3xLadder section, 4 m long (43 kg)
with back protection
3 Climbing procedure
During the climbing operations, the boom column must be
guided and supported by three climbing guide frames.
These frames transfer the occurring forces into the
concrete structure and maintain the stability (Fig 1).
The climbing equipment is always installed on the
lowermost climbing frame.
1. Attach the lifting arms 2 to both climbing cylinders 4 (Fig. 2) and secure the
pins 3.