20
CRACK PRO® GRAVITY FLOW AND DIRECT FIRE MELTER
APPLIES TO ALL LP GAS BURNERS
OPERATING INSTRUCTIONS - LP GAS BURNER
8. As the material temperature gets close to the recommended
pouring temperature, you need to turn the temperature
control #8 down. When constantly adding blocks of material,
the temperature control should be set about 50° higher than
the material pouring temperature.
9. If the material temperature starts to climb over the
recommended pouring temperature, open the lid and add
more blocks. Leaving the lid open will also help drop the
temperature.
POURING MATERIAL
10. Set pour pot or applicator under the material discharge
valve #30 and raise the handle to open.
CAUTION: ALWAYS WEAR LONG SLEEVE SHIRT, GLOVES, AND
A FACE SHIELD WHEN PERFORMING THIS OPERATION!
11. Fill the crack filler pour pot to the desired level and pour into
cracks. Follow with a V-shaped squeegee if desired.
12. To stop for the day, perform the following steps:
• Turn the temperature control #8 knob to its lowest
setting, at least a 1/2 hour before completing work.
• Put agitator control valve #23 in neutral.
• Shut off the engine #21.
• Turn off the propane tank.