DC INVERTER U-MATCH AIR CONDITION MAINTENANCE
153
4. Assemble the new
electronic expansion valve
Assemble the new
electronic expansion valve
to correct position.
During welding, use wet
cloth to wrap the electronic
expansion valve body.
Weld by charging nitrogen,
with the nitrogen pressure
kept at 0.5±0.1kgf/c 󱚸
(relative pressure).
5. Assemble the coil of
electronic expansion valve
After welding of the
connection pipe, mount the
coil according to
disassembly procedures.
Carry out leakage
detection to the system. If no
problem, establish vacuum
and charge refrigerant
through process pipe.
Disassembly and Assembly of electrical parts box
Remark : Before removing the electric box or electric box sub-assembly, make sure that the
power has been cut off.
Step Illustration Handling Instruction
1. Remove the electric box
cover
Cut off the power.
Use the screwdriver to
remove the fixing screws
between electric box cover
and electric box.
Remove the cover from
electric box.
2. Remove the power cables
of motor and other
components
Remove the cables
connecting the electric
elements in the electric box
to the external elements
(e.g. the power cables of
compressor and motor)
Note: When removing the
connection, make sure to