EasyManua.ls Logo

Sinoboom GTJZ1212 - User Manual

Default Icon
92 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
Loading...
GTJZ0612/0612/2146
GTJZ0812/0812/2746
GTJZ1012/1012/3346
GTJZ1212/1212/4047
Operation
Manual
Part No.501043100002
Rev: A
Jul 2020
G T JZ
0608E (2132E)
G T JZ
0808E (2732E)
G T JZ
0808E (2732E)
G T JZ
0808E (2732E)
长沙市宁乡高新技术产业园区金洲大道东
128
0731-87116111 hr@sinoboom . c om . cn ww w .sinoboom . c om . cn
Al w ays F or B e t t er A cc ess Solution s
我们一直在追求新的高
尺寸
210×285mm
20mm
20mm
产品说明书
PRODU C T MAN U AL

Table of Contents

Other manuals for Sinoboom GTJZ1212

Question and Answer IconNeed help?

Do you have a question about the Sinoboom GTJZ1212 and is the answer not in the manual?

Summary

Introduction

Performance Parameters

Machine Components

Safety

Safety Definitions

Alerts to safety statements and symbols.

Electrical Hazards

Covers electrocution, shock risks, and safe distances.

Tipping Hazards

Addresses platform load limits and stability.

Work Environment Hazards

Discusses jobsite conditions and risks.

Unsafe Operation Hazards

Lists actions leading to injury or damage.

Fall Hazards

Safety measures to prevent falls.

Collision Hazards

Awareness and prevention of collisions.

Crush Hazards

Risks of body parts getting trapped.

Fire and Explosion Hazards

Precautions in flammable atmospheres.

Bodily Injury Hazards

Risks from spills and fluids.

Battery Hazards

Safety for battery handling and charging.

Welding and Polishing Safety

Safety protocols for specific maintenance tasks.

Post-Operation Safety

Procedures for safe parking and shutdown.

Jobsite Inspection

Unsafe Operation Hazard (Jobsite)

Emphasizes following safety rules for jobsite operations.

Pre-Operation Inspection

Unsafe Operation Hazard (Pre-Op)

Stresses following safety rules before operation.

Tips for Conducting a Pre-Operation Inspection

Operator responsibilities for inspections.

Conducting a Pre-Operation Inspection

Steps to check machine readiness before use.

Inspecting Parts

Guide for checking individual machine components.

Inspecting Entire Machine

Procedure for checking overall machine condition.

Inspect Hydraulic Oil Level

Importance and steps for checking hydraulic oil.

Inspecting the Battery

Checks for battery performance and safety.

Pre-Operation Function Test

Preparing for Pre-Operation Function Test

Steps to set up for functional testing.

Testing the Ground Controller

Verifying ground control panel functionality.

Testing the Emergency Stop Function

Ensures emergency stops function correctly.

Testing the Lifting and Lowering Functions

Verifies platform lift and lower operations.

Testing the Steering Function

Checks the machine's turning capabilities.

Testing the Driving and Braking Functions

Verifies movement and stopping mechanisms.

Testing the Drive Speed

Checks the machine's speed control.

Testing the Emergency Lowering Function

Verifies the emergency descent procedure.

Testing the Tilt Protection Function

Checks the machine's stability protection.

Testing the Pothole Guard

Verifies the activation of the pothole guard.

Testing the Weighing System (Optional)

Checks the platform load capacity system.

Operating the Machine

Unsafe Operation Hazard (Operating)

General warnings for safe machine operation.

Emergency Stop Function

How to use the emergency stop controls.

Emergency Lowering Feature

Activating the emergency descent.

Emergency Pull;Drag Feature

Procedure for moving the machine in emergencies.

Operating on the Platform

Steps for controlling the machine from the platform.

Operating on the Ground

Steps for controlling the machine from the ground.

Platform Extension Operation

How to adjust the extension platform.

Platform Railings Setup

Procedure for setting up platform railings.

Platform Controller Operation (Ground)

Using the platform controller from the ground.

Driving on a Slope

Guidelines for operating on inclines.

Battery Level Indicator

Interpreting the battery status display.

Charging the Battery

Procedures and safety for charging batteries.

Charger Battery Curve Settings

Adjusting charger settings for battery types.

Indoor;Outdoor Mode Setting

How to set machine mode for indoor/outdoor use.

Transporting and Lifting the Machine

Lifting with a Forklift

Safe procedures for forklift lifting.

Lifting with a Crane

Safe procedures for crane lifting.

Transporting the Machine

Requirements for transporting via trucks/trailers.

Maintenance

Maintenance Safety Warnings

Warnings about improper maintenance.

Pre-Delivery Inspection

Steps for pre-delivery checks.

Maintenance Schedule

Guidelines for routine maintenance intervals.

Completing Repair & Inspection Reports

Procedures for documenting inspections.

Decals;Nameplates Inspection

Safety Label Integrity

Importance of legible and present safety labels.

Sinoboom GTJZ1212 Specifications

General IconGeneral
Load Capacity320 kg
Drive TypeElectric
Gradeability25%
Drive Speed4.5 km/h
Ground Clearance0.1 m
Weight4, 500 kg
TyresSolid
Machine Weight4, 500 kg