8 Dimensions and minimum clearances
SMA Solar Technology AG
Installation Manual 25SCCPXT-SCS_NR-IA-en-12
Minimum clearances for two inverters with mv transformer to be installed outdoors
Option 1
Figure 8: Minimum clearance for two inverters with MV transformer
Position Designation
A Inverter 1
B Inverter 2
C MV transformer and MV switchgear
D Cable route between inverter and MV switchgear