EasyManua.ls Logo

SMA Sunny Tripower CORE2 User Manual

SMA Sunny Tripower CORE2
110 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
Page #1 background imageLoading...
Page #1 background image
Operating manual
SUNNY TRIPOWER CORE2
STP 110-60
STP110-60-BE-en-16 | Version 1.6ENGLISH

Table of Contents

Other manuals for SMA Sunny Tripower CORE2

Question and Answer IconNeed help?

Do you have a question about the SMA Sunny Tripower CORE2 and is the answer not in the manual?

SMA Sunny Tripower CORE2 Specifications

General IconGeneral
Max. DC voltage1100 V
Max. input voltage1100 V
Number of MPP trackers12
Number of independent MPP inputs24
THD< 3%
AC grid frequency50 Hz / 60 Hz
Adjustable AC frequency range45 Hz - 65 Hz
Max. input current per MPP tracker26 A
Operating temperature range-25°C to +60°C
Degree of protectionIP66
Maximum Efficiency98.6%
Max. apparent AC power110000 VA
AC nominal voltage400 V
DC nominal power110000 W
CoolingActive

Summary

Safety

Intended Use

Describes the product's intended use in industrial environments and compliance.

IMPORTANT SAFETY INFORMATION

Provides crucial safety information to be observed at all times when working.

Product Overview

Interfaces and Functions

Describes the product's interfaces and communication capabilities.

Mounting

Requirements for the Mounting Location

Outlines necessary conditions and warnings for selecting a suitable mounting location.

Permitted and prohibited mounting positions

Details the allowed and disallowed orientations for mounting the product.

Recommended clearances for mounting

Specifies required distances to walls and other objects for proper installation.

Mounting to Profile Rails

Provides instructions and requirements for mounting the product using profile rails.

Mounting the Product on a Wall

Step-by-step guide for securely mounting the product onto a wall.

Electrical Connection

Requirements for the electrical connection

Details permitted grid configurations and essential electrical connection requirements.

AC cable requirements

Lists specifications and material requirements for AC cables used with the inverter.

DC cable requirements

Specifies requirements for DC cables, including diameter, cross-section, and voltage rating.

Connecting the AC Cable

Step-by-step procedure for connecting the AC cable, including safety precautions.

Connecting the Grounding

Instructions for performing additional grounding of the inverter for safety.

Connecting the Network Cables

Procedure for connecting network cables, including safety warnings about overvoltage.

DC connection

Overview and assembly instructions for DC connectors.

Connecting the PV Array

Procedure for connecting the PV array, including safety warnings and notices.

Connecting contact for fast stop to digital input

Detailed procedure for connecting a fast stop switch to digital inputs.

Commissioning

Procedure for commissioning in systems without System Manager

Steps for commissioning an inverter without a System Manager.

Procedure for commissioning in systems with System Manager

Steps for commissioning an inverter within a system managed by a System Manager.

Commissioning the Product

Final steps for commissioning the inverter, including checks and switch-on procedures.

Operation

Establishing a connection to the user interface

Guides on connecting to the inverter's user interface via local network.

Direct connection via Ethernet

Instructions for establishing a direct Ethernet connection to the inverter.

Logging into the user interface as an installer

Procedure for logging into the user interface with installer credentials.

Logging into the user interface as a service provider

Procedure for logging into the user interface with service provider credentials.

Changing the Password

Guide to changing user passwords for enhanced system security.

Changing Operating Parameters

Procedure for adjusting operating parameters to optimize inverter performance.

Configuring the Country Data Set

Essential steps to set the correct country data set for grid compliance.

Activating the Fast Stop Function

Procedure to activate the fast stop function via the inverter's user interface.

Updating the Firmware

Instructions for updating the inverter's firmware using an update file.

Disconnecting the product from voltage sources

Event messages

Event 002 (Sunny Portal: 103)

Details "Grid overvoltage" event, explanation, and corrective measures.

Event 003 (Sunny Portal: 102)

Details "Temporary grid overvoltage" event, explanation, and corrective measures.

Event 004 (Sunny Portal: 104)

Details "Grid undervoltage" event, explanation, and corrective measures.

Event 005 (Sunny Portal: 203)

Details "Low voltage" event, explanation, and corrective measures.

Event 007 (Sunny Portal: 6603)

Details "Temporary AC overcurrent" event, explanation, and corrective measures.

Event 008 (Sunny Portal: 503)

Details "Grid overfrequency" event, explanation, and corrective measures.

Event 009 (Sunny Portal: 502)

Details "Grid underfrequency" event, explanation, and corrective measures.

Event 010 (Sunny Portal: 1302)

Details "Grid power failure" event, explanation, and corrective measures.

Event 013 (Sunny Portal: 1501)

Details "Supply grid fault" event, explanation, and corrective measures.

Event 014 (Sunny Portal: 103)

Details "10-minute grid overvoltage" event, explanation, and corrective measures.

Event 015 (Sunny Portal: 103)

Details "Grid overvoltage" event, explanation, and corrective measures.

Event 017 (Sunny Portal: 1416)

Details "Unbalanced load of grid voltage" event, explanation, and corrective measures.

Decommissioning

Disconnecting product connections

Step-by-step guide to safely disconnect all product connections.

Disassembling the product

Instructions for safely disassembling the product for removal or transport.

Replacing the Product with a Replacement Device

Maintenance

Safety during Maintenance

Critical safety precautions to be observed during maintenance activities.

Technical Data

Related product manuals