9 Commissioning
SMA Solar Technology AG
Operating manualSTP110-60-BE-en-1652
9 Commissioning
9.1 Procedure for commissioning in systems without
SystemManager
This section describes the procedure of commissioning an inverter that is configured individually
and used in systems without SystemManager (e.g. SMA Data Manager or an inverter that is
configured as System Manager).
It provides an overview of the steps, which must be performed in the prescribed sequence.
Procedure See
1. Commission the inverter. Section9.3, page53
2. Establish a connection to the user interface
of the inverter. There are various connec-
tion options to choose from for this:
• Direct connection via Ethernet
• Connection via Ethernet in the local
network
Section10.1, page55
3. Log into the user interface. Section10.2, page56
4. Set country data set. Section10.9, page62
5. Make further inverter settings as needed. Section10, page55
9.2 Procedure for commissioning in systems with
SystemManager
This section describes the procedure of commissioning an inverter that is used in systems with
SystemManager (e.g. SMA Data Manager or an inverter that is configured as System Manager).
In this case, the inverter is controlled or regulated by the SystemManager.
It provides an overview of the steps, which must be performed in the prescribed sequence.
Procedure See
1. Commission the inverter. Section9.3, page53
2. Commission the System Manager. Manual of the SystemManager
3. Register the inverter as an SMA Speedwire
device in the SystemManager and make
the initial configuration of the inverter via
the SystemManager. The configuration is
transferred to the inverter and the settings
of the inverter are overwritten.
Commissioning Assistant of the
SystemManager