6 Mounting
SMA Solar Technology AG
Operating manual STP110-60-BE-en-16 27
6.5 Mounting to Profile Rails
6.5.1 Requirements for the profile rails
The profile rails must be designed for the load and orientation of the inverters in the PV system.
The profile rails might need to be reinforced.
The spacing of the profile rails must be designed for the spacing of the holes in the bracket
parts for the mounting bracket.
683
1031
1117
262
392.5
Figure 5: Dimensions of the mounting bracket (dimensions in mm)
6.5.2 Mounting the Product to Profile Rails
CAUTION
Risk of injury due to weight of product
Injuries may result if the product is lifted incorrectly or dropped while being transported or
mounted.
Transport and lift the product carefully. Take the weight of the product into account.
Wear suitable personal protective equipment for all work on the product.
Transport the product using the carrying handles or hoist. Take the weight of the product
into account.
Use all carrying handles provided during transport with carrying handles.
Do not use the carrying handles as attachment points for hoist equipment (e.g. straps, ropes,
chains). Insert eye bolts into threads provided on top of the product to attach the hoist
system.