13 Decommissioning
SMA Solar Technology AG
Operating manual STP110-60-BE-en-16 97
15. Tighten the swivel nut on the cable gland hand-tight.
16. Move the limiting lever back to its original position and close the cable compartment cover.
17. Disassemble the product (see Section13.2, page97).
13.2 Disassembling the product
Requirements:
Original packaging or packaging suitable for the weight and dimensions of the product must
be available.
A pallet must be available.
Mounting material for attaching the packaging on the pallet must be available (e.g. tie-down
straps).
All transport handles must be in place.
Procedure:
1. Tighten the two screws on the cable compartment
cover (TX30, tightening torque: 4.3Nm).
2
2x2x2x
1
2. Remove the screws to attach the inverter to the mounting bracket (PH3).
3. Remove the sealing screws on the attachment bars of the inverter using a flat-blade
screwdriver (4mm).
4. If the inverter is to be lifted out of the mounting
bracket using lifting gear, screw the eye bolts into
the 2 upper threaded holes on the right-hand and
left-hand side of the inverter and attach the lifting
gear to them. The lifting gear must be suitable to
take the weight of the inverter.