9 Commissioning
SMA Solar Technology AG
Operating manual STP110-60-BE-en-16 53
Procedure See
4. Establish a connection to the user interface
of the inverter. There are various connec-
tion options to choose from for this:
Direct connection via Ethernet
Connection via Ethernet in the local
network
Section10.1, page55
5. Log into the user interface. Section10.2, page56
6. Ensure that the country data set has been
configured correctly.
Section10.9, page62
7. Make further inverter settings as needed. Section10, page55
9.3 Commissioning the Product
Requirements:
The AC circuit breaker must be correctly rated and mounted.
The product must be correctly mounted.
All cables must be correctly connected.
Unused enclosure openings must be sealed tightly with sealing plugs.
Procedure:
1. Close the cable compartment and tighten the screws
on the cable compartment cover (TX 30, torque:
4.3Nm).
2
2x2x2x
1
2. Switch on all 4 DC load-break switches.