IM-P402-44 AB Issue 15
19
Verification Signatures
Clearance Checking
Date Reason for test 14 mm ( ") wires Independent
or more removed assessor
- WARNING: It is essential to remove the checking wires from the probe before
commissioning the boiler or vessel. Failure to do this could stop the low water alarms
operating.
- The person who removes the checking wires must sign the record sheet to verify that this has
been completed.
- Independent assessor: It is strongly recommended that an independent person (who might
be an Insurance Inspector, for example) verifies:
- That the test has been carried out.
- That the checking wires have been removed.
- That the record sheet has been correctly completed by a competent person.