5.1
Ensure that the installation is correct (Figure 1, page 5).
5.2
Blow through the pipework to ensure that it is completely free of any foreign matter that may other wise
pass to the valve seat and cause damage, leading to seat leakage. Blowdown must be carried out
before installing the safety valve.
5.3
Ensure that valve is set to the correct pressure, see 'Testing during use', Section 9.
Normally, the valve will be supplied set at the required pressure and sealed.
Setting of Spirax Sarco safety valves must only be carried out by authorised, competent persons.
Spirax Sarco accepts no responsibility for valves which have been reset by unauthorised persons.
4.1
Valves should be transported in the upright position.
4.2
Do not drop and avoid sudden shocks or heavy impacts.
4.3
Always store in the suppliers packaging until required.
4.4
Never carry a safety valve by the lifting lever.
3. Supply
4. Handling
5. Before fitting the valve