C. Check the parts before assembly.
1. Packaged lift and hydraulic power unit (
See Fig. 6).
2
. Move aside the lift with fork lift or hoist, and open the extension packing carefully
,
t
ake off the lifting arms and parts box from upper and inside the column, then mov
e
th
em to location nearby installation site, check the parts according to the shipment
parts list
(See Fig.7).
3. Loose the screws of the upper package stand, take off the upper extension columns,
take out the parts in the inner column and remove the package stand
4. Move aside the parts and check the parts according to the shipment parts list
(See Fig.8, 9).
Assy.
Name plate
(Outer Column)
Parts in the shipment parts list
Fig. 9
Parts in the parts box (96)