1. Load cabinets onto lift.
2. -Operate the winch to raise cabinets into place.
-Lock brake on Dolly Base.
-Level cabinets and fasten in place.
The Dolly Base can be used independantly to move
Cabinets
INSTALLING UPPER CABINETS
(before base cabinets)
INSTALLING UPPER CABINETS
(over existing base cabinets)
Using the Dolly Base
Configuration (p. 3) to install
upper cabinets first (before
base cabinets are in place).
Using the Counter Base
Configuration (p. 4) to install
upper cabinets second (when
base cabinets are in place).
Questions? Problems?
Call
701-775-0551
1-800-448-0822
5
1. Start by using the Dolly Base Assembly to raise the
upper cabinets to blocks (approx. 9” high, blocks not
included) on the base counters.
2. Use the Counter Base Conguration (p. 4) for nal
positioning of the cabinets.
Center the Cabinetizer
TM
under the load, making sure
the weight of the load is balanced on the lift.
Operate the winch to raise cabinets into place.
Level cabinets and fasten in place.
•
•
•