Greenhouse Installation Procedures

Step 1: Site Selection and Preparation

Choose and prepare a suitable installation site, ensuring a solid, level ground.

Step 2: Assemble Trusses

Assemble the front, rear, and middle trusses using specified parts and figures.

Step 3: Erect Trusses

Position and secure all assembled trusses to the base plates with fasteners.

Step 4: Install Purlins and Front;Rear Trusses

Install purlins and structural members for the front and rear truss sections.

Step 5: Install Boards and Reed Groove

Attach boards and reed grooves to the frame using self-tapping screws.

Step 6: Install Cover Panels

Affix front and rear film panels to the structure using clip springs and buckles.

Step 7: Install Film and Roll System

Mount the roof cover film and the roll film system components.

Post-Installation and Maintenance

Final Inspection and Care

Perform final checks on connections and follow care advice for longevity.

TMG INDUSTRIAL 25100 Specifications

General IconGeneral
Panel Thickness4 mm
UV ProtectionYes
Assembly RequiredYes
Materialpolycarbonate panels
Warranty1 year limited warranty