CHECK BEFORE OPERATION
Air Supply
DANGER
Follow Lock-out / Tag-out (LOTO) procedures for all process and energy connections.
WARNING
All air supply system components must be rated for the service conditions present.
Air supply is capable of supplying adequate air volume (at least 90cfm per unit)
Air supply is capable of supplying adequate air pressure (at least 100 psig)
Air supply is connected to ZEVAC in a secure fashion
Air supply connection piping / hoses have been verified to be leak-free
Air regulator is set to deliver adequate pressure to ZEVAC (100 – 250 psi)
VERIFY Hose halters are in place on all hose connections
Inlet Connection
DANGER
Follow Lock-out / Tag-out (LOTO) procedures for all process and energy connections.
WARNING
All gas system components must be rated for the service conditions present.
Identify inlet gas connection
Verify inlet gas connection has isolation valve
Inlet Gas Connection is connected to ZEVAC in a secure fashion
Inlet Gas piping / hoses have been verified to be leak-free
Inlet Gas piping has an isolation valve
Verify hose halters are in place on ZEVAC inlet gas hose.
Discharge Connection
DANGER
Follow Lock-out / Tag-out (LOTO) procedures for all process and energy connections.
WARNING
All gas system components must be rated for the service conditions present.
Identify discharge gas connection