Unit Clearances, Curb Dimensions, and Dimensional Data
OAU-SVX007A-EN 31
OAB Units
Unit Clearances
Note: Certain options require auxiliary cabinet. Refer to
project-specific unit submittals.
Curb Dimensions
Figure 34. Typical installation clearances for OAB unit
7'-0"
6'-0"
END TO END
3'-0"
4'-0"
4'-0"
3'-0"
Figure 35. Typical installation clearances for OAB unit
with auxiliary cabinet
Figure 36. Unit curb data for OAB 3–9 tons


(1'72(1'















6833/<
5(7851