EasyManua.ls Logo

Trillium WSP-6 User Manual

Default Icon
73 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
Page #1 background imageLoading...
Page #1 background image
Self-Priming Pumps
Installation, Operation & Maintenance Instructions
Model WSP-6
WSP-D300_6
Trillium Flow Technologies
Tel: 801-359-8731
Fax: 801-530-7531
© Copyright 2019, The Factory. All rights reserved.

Table of Contents

Question and Answer IconNeed help?

Do you have a question about the Trillium WSP-6 and is the answer not in the manual?

Trillium WSP-6 Specifications

General IconGeneral
BrandTrillium
ModelWSP-6
CategoryWater Pump
LanguageEnglish

Summary

I. INTRODUCTION

II. SAFETY

III. PREVENTIVE MAINTENANCE

IV. DISASSEMBLY & REASSEMBLY OF THE PUMP & SEAL

A. REMOVING THE COVER PLATE & WEARPLATE

Details the process of removing the cover plate and wearplate from the pump.

B. REMOVING THE SUCTION CHECK VALVE

Outlines the steps for removing the suction check valve assembly.

C. REMOVING THE ROTATING ASSEMBLY

Describes the procedure for removing the pump's rotating assembly.

D. REMOVING THE IMPELLER

Explains how to detach the impeller from the shaft.

E. REMOVING THE SEAL

Details the process of removing the mechanical seal from the shaft.

F. REMOVING & DISASSEMBLING THE SHAFT & BEARING

Covers the disassembly and removal of the shaft and bearing components.

G. DISASSEMBLY OF THE TWO-PIECE BEARING HOUSING

Explains how to disassemble the two-piece bearing housing if necessary.

H. REASSEMBLING THE TWO-PIECE BEARING HOUSING

Details the reassembly process for the two-piece bearing housing.

I. REASSEMBLING & INSTALLATING THE SHAFT & BEARING

Guides on reassembling and installing the shaft and bearing.

J. INSTALLING THE MECHANICAL SEAL

Provides instructions for installing a new mechanical seal.

K. INSTALLING & ADJUSTING THE IMPELLER

Details the installation and adjustment of the impeller.

L. INSTALLING THE ROTATING ASSEMBLY

Outlines the procedure for installing the rotating assembly into the pump casing.

M. INSTALLING THE SUCTION CHECK VALVE

Describes how to install the suction check valve assembly.

N. INSTALLING & ADJUSTING THE BACK COVER

Explains the installation and adjustment of the back cover.

V. MAINTAINING THE PRESSURE RELIEF VALVE

VI. LUBRICATION

A. Seal Cavity

Details lubrication requirements for the seal cavity.

B. Bearing Cavity

Outlines lubrication for the bearing cavity.

C. Power Source

Refers to power source lubrication requirements.

VII. TROUBLESHOOTING

VIII. INSTALLATION

A. PUMP DIMENSIONS

Provides information on the physical dimensions of the pump.

B. INSPECTION PRIOR TO INSTALLATION

Details the pre-installation inspection checklist for the pump.

C. PUMP POSITIONING

Covers lifting, mounting, and clearance for pump placement.

D. SUCTION AND DISCHARGE PIPING

Discusses piping materials, configuration, connections, and gauges.

E. SUCTION LINES

Provides guidelines for suction line fittings, strainers, sealing, sump installation, and positioning.

F. DISCHARGE LINES

1. Siphoning

Discusses avoiding siphoning in discharge lines to prevent pump damage.

2. Valves

Covers the use and type of valves in discharge lines for throttling and safety.

3. Bypass Lines

Details the installation and sizing of bypass lines for priming and operation.

G. WSP™ AUTOMATIC AIR RELEASE VALVE (WSP™ ARV)

1. Theory of Operation

Explains how the WSP™ ARV functions during priming and operation.

2. WSP™ Air Release Valve Installation

Provides instructions for installing the WSP™ ARV on the pump discharge line.

H. ALIGNMENT

1. Coupled Drives

Aligns shafts in vertical and horizontal planes using couplings for mechanical accuracy.

2. Spider Insert-type Couplings

Details alignment for spider insert-type couplings using calipers for precision.

3. Non-Spider Type Couplings

Describes alignment for non-spider couplings using feeler gauges for accuracy.

4. V-Belt Drives

Covers alignment of pulleys for V-belt drives to ensure proper power transmission.

IX. OPERATION

A. Priming

Explains the process of priming the pump and piping, ensuring it's ready for operation.

B. START-UP

Details procedures for starting up the pump and motor correctly.

C. OPERATION

Covers pump operation with/without bypass, leaking, temperature, vacuum, and strainer checks.

D. STOPPING

Outlines procedures for safely stopping the pump, including cold weather preservation.

E. CHECKING THE BEARING TEMPERATURE

Explains how to check bearing temperatures using a thermometer for operational health.

X. TECHNICAL DATA

A. 6" WSP Curve

Presents performance curves for the 6" WSP pump, showing head, flow, and efficiency.

B. 6" WSP General Arrangement

Shows the general arrangement drawing and dimensions of the 6" WSP pump.

C. 6" WSP Sectional Drawing and Parts List

Related product manuals