EasyManua.ls Logo

Tyco F3200 - Page 210

Tyco F3200
284 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
F3200 Installation & Programming Manual Document No: LT0122
Alignment, Adjustment & Placing into Operation
Page 10-6 5 July 2001 Issue 2.7
COMMISSIONING CHECKLIST (CONTINUED)
3. POWER SUPPLY
A) Mains Wired correctly, MOV, cap fitted
B) "Mains Isolate Switch" and "NAE" label fitted
C) Mains Earth wired to stud, good contact
D) Mains Switch neon off/on for switch off/on
E) MAF/PSU Mains On LED on, Fuse Blown LED off
F) VRECT at DC IN tab 40-42Vdc
G) Charger Voltage 27.25-27.4V warm, 27.5-27.75V cold
4. OPERATION
A) LEDs flash, aligned with windows, "MAINS ON" LED on
B) Buzzer pulses with microswitch operated, Lk7 in Write
C) Controller LK7 in "Protect" position
D) LCD contrast correct for front view
E) De-isolate zones, system test pass on all (8) circuits
F) FIP MCP Programmed to Zone 1; Other: ___________ OK
G) "ALM" LED flashes & buzzer pulses for MCP operation
H) Acknowledge silences buzzer, Zone Resets
I) Controller Lk2 fitted (not in Service mode)
SERIAL NUMBER TEST PASSED
DATE : ………............. SIGNATURE : ……………….......................

Table of Contents

Other manuals for Tyco F3200

Related product manuals