EasyManua.ls Logo

VADA VFB-HM110 - Page 22

Default Icon
56 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
22 VADA FLOW BOSS HORIZONTAL MULTISTAGE PUMP VFB-HM110 INSTALLATION MANUAL
Adjust the Cut-In Pressure
After installing the VFB-APC and VFB-MSU25,
the cut-in pressure must be adjusted to ensure
a smooth and reliable changeover.
1. Turn on the Pump and VFB-APC.
2. Locate the adjustment screw at the back
of the VFB-APC.
3. Using a flat head screwdriver, turn the
adjustment screw clockwise until you reach
the correct pressure (roughly, this will be
3.5 full 360° turns).
4. Confirm the pressure has been correctly
adjusted by slowly opening an outlet and
checking the gauge on the side of the
VFB-APC. If the pump starts when the
gauge drops to 2.2 bar the cut in pressure
has been successfully adjusted.
5. Your pump solution is now ready of
operation!
INSTALLATION
ON
Solid level base
To house Mains water in

Related product manuals