EasyManuals Logo

Vanderbilt GM730 Application Guide

Vanderbilt GM730
66 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #48 background imageLoading...
Page #48 background image
7
Commissioning
48
Vanderbilt
Seismic Detectors Application Guide
I-200153-1
08.2016
Figure 7-1: Staged commissioning - shock
In Figure 7-1: Staged commissioning - shock the shock test will illuminate the LED as confirmation of
the alarm and the voltage will increase to circa 2.7v DC level as confirmation.
Do not strike the detector as this may cause irreparable damage to the detector.
Figure 7-2: Staged commissioning - integration
In Figure 7-2: Staged commissioning - integration the integration test will illuminate the LED as confir-
mation of the alarm and the voltage will increase to circa 2.7v DC level as confirmation.
The recommended method of recording and verifying the tests is to use the GMXD7 SensTool. See
Section 8 SensTool for additional information.

Table of Contents

Other manuals for Vanderbilt GM730

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Vanderbilt GM730 and is the answer not in the manual?

Vanderbilt GM730 Specifications

General IconGeneral
BrandVanderbilt
ModelGM730
CategorySecurity Sensors
LanguageEnglish

Related product manuals