4.2 Handling the Unit while Packaged
If possible, transport the unit with a forklift
When using a forklift:
Make sure that the lift has adjustable forks, and are spread to the widest allowable distance to still fit under the
skid.
Make sure that the fork length is suitable for the skid length. Skid length is 128in. (3251mm).
If the unit must be lifted higher than 2in.(51mm) to 4in. (102 mm), all personnel not directly involved in
moving the unit must be 20ft. (5m) or farther from the unit.
4.3 Unpacking the Unit
Remove exterior package material from around, and on top of the unit.