Operation Manual / TPS44-F.. - TPS61-F..
Start-up 3
Commissioning after taking out of
operation
3.3 Page 41
© Copyright 2016 ABB. All rights reserved.
August 2017HZTL2412_ENRevision F
Commissioning after taking out of operation
3.3
τ Remove cover plates (blind flanges) between compressor casing out-
let and charge air duct, before gas inlet and after gas outlet.
τ Inspect exhaust gas duct / line in front of and after turbine for any
combustion deposits, foreign matter or residual water. Clean and re-
move.
τ Inspect air supply line or filter silencer for any foreign matter. Clean
and remove.
τ Start up turbocharger oil circulation system at engine end.
τ Prepare turbocharger for operation as instructed in section "Inspection
work before start-up / commissioning" of chapter headed "Start-up /
commissioning".
τ Start up turbocharger.
If provided