EasyManuals Logo

ABB TPL67-C Series User Manual

ABB TPL67-C Series
138 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #67 background imageLoading...
Page #67 background image
Operation Manual / TPL67-C.. - TPL71-C..
Maintenance
5
Cleaning turbine blades and nozzle ring
in operation
5.4
Page 65
© Copyright 2017 ABB. All rights reserved.
February 2017 HZTL2488_EN Revision D
Layout of cleaning pipes
Wet cleaning procedure for turbine during operation
Meet prerequisites and operating state requirements without fail before
cleaning!
Make sure water supply (01) is connected, turned on and guaranteed.
Open drain pipe (08, 09), if provided.
Switch over 3-way valve (04) from scavenging air mode to water sup-
ply.
Set the required volume of water on the flowmeter as shown in the ta-
ble (see table Cleaning parameters).
Shut off the water supply again by switching the 3-way valve (04) to
scavenging air mode after injecting the required volume of water.
The injection process has been completed.
Close drain hole (if provided) above drain pipe (08, 09).
After cleaning, wait with engine running for at least 10 minutes without
changing load to allow turbocharger to dry.

Table of Contents

Other manuals for ABB TPL67-C Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB TPL67-C Series and is the answer not in the manual?

ABB TPL67-C Series Specifications

General IconGeneral
BrandABB
ModelTPL67-C Series
CategoryIndustrial Equipment
LanguageEnglish

Related product manuals