Operation Manual / TPL69-A10 / -A30 ... TPL77-A10 / -A30
5 Maintenance / 5.3 Cleaning the compressor during operation
© Copyright 2018 . All rights reserved. HZTL2481_EN Revision C May 2018
5.3.1 Wet cleaning with orifice plate on filter silencer (XC2)
Wet cleaning procedure for compressor with XC2
u Trigger water injection according to the specifications of the en-
ginebuilder.
u The specified water pressure upstream of the connection to the tur-
bocharger must be maintained.
u Operate engine for at least five additional minutes after cleaning.
Not more than three cleaning cycles should be conducted consecutively.
Cleaning parameters for XC2 for each turbocharger compressor
Product Engine load Water pres-
sure
[bar]
Water
injection time
[sec]
Ø orifice
[mm]
TPL73-A 50…85% 2 10 2.5
TPL77-A 2.9
Page 53 / 136

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB TPL69-A Series and is the answer not in the manual?

ABB TPL69-A Series Specifications

General IconGeneral
BrandABB
ModelTPL69-A Series
CategoryIndustrial Equipment
LanguageEnglish

Related product manuals